SCHEDULE

Fall/Winter 2017:

Prepare draft State Environmental Study

Fall/Winter 2018:

Perform additional analysis and design of
Fox Hills intersection

Spring/Summer 2019:

Property acquisition negotiations, update interchange design

Spring 2020 - *Spring 2021:

Interchange construction

*Bangerter mainline complete by Fall 2020

Spring 2018:

Public hearing, comment period and finalize Study

Spring 2019:

Draft State Environment Study Reevaluation, comment period, and finalize Study

Summer/Fall 2019:

Aqueduct relocation construction